E Light’s team is the prime contractor on United Power’s 80 MW BESS (Battery Energy Storage Systems) in Weld County, Colorado. Over 5,500 yards of concrete has been placed throughout the Colorado winter. Winslow crane service supported the team setting the 80,000 lb. battery packs and aux equipment. The kitting and assembly was completed at the office in Englewood, and E Light was able to reduce our onsite installation time by 2 weeks. The complete SCADA rack assembly was installed in hours, not weeks.