General Contractor:
Ameresco
Owner:
Nucor Steel

E Light was responsible for the full EPC scope on this 58 MW battery energy storage system project in Kingman, AZ. The team provided structural, civil, mechanical, and electrical design; self-performed substation upgrades; and integration with the steel plant for customer Nucor Steel. Spanning from November 2024 to March 2025, the project finished an impressive five months early.